Mr. Speaker Sir, in terms of disaster management, the prevalence of fire disaster incidences has destroyed lives and valuable property. Good examples include the Mpilo Hospital, Kwekwe General Hospital, Southampton House for Zimbabwe Republic Police in Bulawayo, Mutare bus accident and many other fire incidences in rural areas resulting from uncontrolled veld fires. Meanwhile, the Ministry has given instructions to sub-national structures of the civil protection systems in this country to carry out an inventory of all emergency services in order for us to come up with reinforcement skills to improve the coverage of the same. This is in line with provisions of Section 23 of the Civil Protection Act [Chapter 10:06] of 1989 in conjunction with the Urban Councils Act and Rural District Councils Act. Local authorities are mandated to protect lives and property at law to provide relief, response and recovery throughout the disaster management cycle.
Government of Zimbabwe entered into a bilateral agreement with the Belarusian Government for the supply of a variety of equipment. This was necessitated through the existing cordial bilateral relations between the two countries. Through the Government, a request for model equipment whose specifications are tailor-made to suit the local terrain was made by the local authorities. Physical visits were also made to Allied Timber premises who procured the same to ascertain the type of equipment the Ministry was procuring. On approval from the relevant stakeholders, Government facilitated the purchase and negotiated for staggered payment terms. The initial decision by Ministry was for the money for emergency services to be channelled through the department of Civil Protection. However, the Ministry of Finance and Economic Development decided that the recapitalization of local authorities be supported through the devolution funds. The staggering of payments done using devolution funds and/or own funds provide relief to local authorities as they can spread their cash flow over a defined period of 12 months. It is within the confines of Government thrust to ensure that local authorities are fully capacitated for them to provide adequate and requisite municipal services which include emergency services.
In such instances where bi-lateral agreements are made, the role of Local Procurement Authorities does not apply. On this note, reference is made to the Public Procurement and Disposal of Public Assets Act, Section 3 (2) (a).
Application of the Act
To the extent that this Act conflicts with an obligation of Zimbabwe under or arising out of any convention, treaty or agreement between Zimbabwe and one or more foreign states or governments.
The procurement procedure and cost benefit analysis
Submissions to the Ministry indicated that regional producers of such equipment have their prices pegged at around $500.000 plus as confirmed by the forum to the Ministry in some discussions. This is significantly higher than the price of $464.296 offered from Belarus. This total cost includes the truck, firefighting equipment and the requisite technology.
Compatibility of Equipment
The fire tenders from Belarus have been tailor-made to suit our local terrain with approved requisite specifications as per client local authorities’ request – hence, the efficiency and effectiveness of the equipment cannot be doubted.
Backup and support services
The package from the suppliers includes backup and support services, training of operators here in Zimbabwe and in Belarus. The Ministry is fully convinced that every procedure, consultations and engagements done in relation to this matter were above board given the priority to deal with fire related hazards in rural and urban communities.