The Zimbabwe Power Company (ZPC) sent out a total of 2029.88GWh of electricity against a target of 2124.59GWh in the third quarter of 2017, missing the production target for the quarter by 4.46 percent leading to resumption of load shedding in some parts of the country.
In a quarterly update ZPC managing director Noah Gwariro said performance was affected by forced outages at Hwange Thermal Power Station and other smaller stations around the country.
“Hwange failed to meet its target as a result of the delayed return to service of Unit 6 from major overhaul, numerous tube leaks as well as milling plant challenges,” he said.
“Output at the Small Thermals was constrained due to low availability of the boiler and turbine plant, as well as unavailability of coal”.
Gwariro said coal suppliers had fallen short of their delivery targets for the quarter resulting in depleted stock levels at the Thermal Stations.
Year on year output sent out was 7.75 percent lower at 5430 GWh against a target of 5886 GWh.
He added water levels at lake Kariba dropped from 483.19m at the end of the second quarter to 481.99m (46.89 percent full) at the end of September 2017.- The Source
(292 VIEWS)
Zimbabwe is among the top 30 countries in the world with the widest gap between…
Zimbabwe’s battered currency, the Zimbabwe Gold, which was under attack until the central bank devalued…
Plans by the ruling Zimbabwe African National Union-Patriotic Front to push President Emmerson Mnangagwa to…
The Zimbabwe government’s insatiable demand for money to satisfy its own needs, which has exceeded…
Economist Eddie Cross says the Zimbabwe Gold (ZiG) will regain its value if the government…
Zimbabwe’s capital, Harare, which is a metropolitan province, is the least democratic province in the…