Categories: Stories

Tough quarter for Bindura Nickel

A tough quarter for the country’s biggest nickel producer paints a stark picture of the pressures that Zimbabwean miners are facing – collapsing metal prices abroad, plus rising costs and low capital at home.

Bindura Nickel Corporation (BNC) didn’t mine any nickel at all during the period because of equipment failure. This is happening at a time when nickel prices fell 48% last year, while costs of production soared at home.

The company reports the failure of its Sub-Vertical Rock Winder (SVR) bull gear, the equipment used to lift ore from underground. To install new equipment, the company had to shut down the plant last September. Installation is only expected to be completed this quarter after BNC faced more technical problems. This means that BNC has not produced or sold any nickel for months.

“As a result of the shutdown referred to above, no ore was mined or milled, and no nickel in concentrates were produced during the third quarter of Financial Year 2024. In the comparable period, the company mined 51 770 tonnes of ore, milled 50 907 tonnes of ore, and produced 275 tonnes of nickel in concentrate,” BNC reports in an update.

BNC, a subsidiary of Kuvimba Mining House, mirrors the crisis of most Zimbabwean mining firms – they are short of capital to reinvest in their mines at a time when metal prices are falling and costs are rising.

Says BNC: “Currently, the Company is faced with several challenges that threaten the survival of the business and the restart of the mine following the replacement of the SVR bull gear. These challenges include low nickel prices on international markets, high domestic input costs, particularly electrical power costs which have increased by more than 60% over the last 16 months, and the need for capital to refurbish underground mining mobile equipment and the concentrator plant, and development of the mine which has been lagging for the past two decades.”

Nickel prices are forecast to remain low this year because of surplus production from China and Indonesia.

On resources, BNC’s tale is a familiar story across the industry; there is vast potential, but little capital to exploit it. Trojan Nickel Mine sits on around 13.13 million tonnes of nickel ore at an average grade of 0.97%. This substantial resource gives a life of mine of at least 10 years at maximum design production capacity. However, the company does not have the capital needed to mine the resource.- NewZWire

 

(50 VIEWS)

Don't be shellfish... Please SHARE
Google
Twitter
Facebook
Linkedin
Email
Print

This post was last modified on February 19, 2024 6:21 pm

Charles Rukuni

The Insider is a political and business bulletin about Zimbabwe, edited by Charles Rukuni. Founded in 1990, it was a printed 12-page subscription only newsletter until 2003 when Zimbabwe's hyper-inflation made it impossible to continue printing.

Recent Posts

Tshabangu says it will take 67 years to complete the Bulawayo-Nkayi Road at the current pace

Senator Sengezo Tshabangu yesterday expressed dismay at the pace at which the government is constructing…

May 10, 2024

Zimbabwe to fine those breaching official exchange rate US$15 000 or more

Zimbabwe has ordered providers of goods and services to use the official exchange rate or…

May 10, 2024

Zimbabwe to introduce legislation to ensure official exchange rate is used for pricing

Zimbabwe is going to introduce legislation which ensures that the country uses one exchange rate…

May 8, 2024

Are Zimbabweans giving social media more credit than it deserves?

The role of social media on how people get their news in Zimbabwe is being…

May 3, 2024

Top 20 countries in debt to China- Zimbabwe is not one of them

Ten African countries are amongst the biggest debtors to China, but Zimbabwe is not among…

May 1, 2024

Is Zimbabwe now on the right track?

The Reserve Bank of Zimbabwe’s Monetary Policy Committee, which met on Friday last week, says…

April 30, 2024