Parliament takes Gumbo to task over the Beitbridge-Harare Road dualisation

HON. CROSS: Mr. Speaker Sir, may I follow that up.  Mr. Speaker, the Minister has still not given me a clear explanation, I accept that maybe Geiger is a financier, but the question is; how are they going to award the actual construction tenders?  Will Geiger go at international tender or have they agreed a price on a cost price basis?  This is because, unless we go to tender on an open tender, transparent basis, there are at least five of six companies in Southern Africa which can do that job with their hands tied behind their back.  I heard you have various prices – $3 billion, $2 billion, $1 billion, I do not know what they are talking about, I do not know how these prices were established. 

As far as I am concerned, the critical element is that when we go to award the actual tenders for these specific construction elements, that should be done by open public tender within the region.  I just want to know what is the Minister’s intentions regarding his policy towards that specific aspect because I do not see otherwise how we are going to get a price.  This is a major project.

HON. DR. GUMBO: Thank you Mr. Speaker Sir. I think it is very important that even all Members of Parliament know what exactly is happening because at the end of the day, it is a loan to the Government.  I am very grateful that the Hon. Member continues to probe for more information.  Mr. Speaker Sir, an open tender was flighted it was not a closed tender. 

Mr. Speaker Sir, a tender was made international and all our ambassadors got the tender and companies, not only Geiger responded to that tender.  It was an open tender.  Maybe I can give more information, the section from Beitbridge to Harare, for Geiger, they offered a $984 million, but what we had as a reserve was actually about $1 billion for that section.  Then the section from Harare ring road is quoted at $368 million, then the section from Harare to Chirundu, $686 million.  So, those figures are there.  It was on that basis and also on the feasibility studies that had been done, that it was found fair to accept Geiger, which had offered a lower figure than what was offered by other companies and also what the feasibility study had asked for.  So, it was really an open tender and not a closed one. 

HON. MAONDERA: On a point of privilege Mr. Speaker Sir.

THE HON. SPEAKER: No, you cannot do that, you better ask a supplementary question.

HON. MAONDERA: Alright, I can ask a supplementary.  Thank you.  Hon. Minister, sometime in May last year, there was pomp and fanfare at Chaka there, with the former President ground-breaking that road that was going to commence in three months time.  Can you tell this House why it has taken so long to start the road, given the fact that people are dying, it is so horrendous.  People are dying every day in that road.  The image that the road is giving to Zimbabwe is so bad because it is a link road with most trucks coming from Zambia to South Africa.  Why has it taken more than a year now to commence work on that road?

HON. DR. GUMBO: Thank you Mr. Speaker Sir.  It is very true that a ground breaking ceremony was held on the 17th of May, 2017 at Chaka Business Centre, it is a fact.  However, it remains for Hon. Members to know that on projects of this magnitude, they are not done overnight  – [HON. MEMBERS: Inaudible interjections.] – Mr. Speaker Sir, when the ground-breaking was done, the contractor and the financier were present and they made the promise that they would be starting their construction in three months, they did mention that.  It was not because of me, it was because of the contractor.  The contractor mentioned that information to all of us and it is only fair that I could speak on that because I was the Minister responsible and that is acceptable. 

The point I want to make Mr. Speaker Sir, is that having said that, there were other issues precedent to the implementation of the project and that could not be primarily be blamed on the Geiger company and its contractor.  There were also issues on our side which were to be met or issues precedent – declaration of project national status, the opening of the accounts – [HON. MEMBERS: Inaudible interjections.] – I think you want me to give you information, is that so?

Continued next page

(554 VIEWS)

Don't be shellfish... Please SHARE
Google
Twitter
Facebook
Linkedin
Email
Print

This post was last modified on March 15, 2018 9:12 am

Page: 1 2 3 4

Charles Rukuni

The Insider is a political and business bulletin about Zimbabwe, edited by Charles Rukuni. Founded in 1990, it was a printed 12-page subscription only newsletter until 2003 when Zimbabwe's hyper-inflation made it impossible to continue printing.

Recent Posts

Are Zimbabweans giving social media more credit than it deserves?

The role of social media on how people get their news in Zimbabwe is being…

May 3, 2024

Top 20 countries in debt to China- Zimbabwe is not one of them

Ten African countries are amongst the biggest debtors to China, but Zimbabwe is not among…

May 1, 2024

Is Zimbabwe now on the right track?

The Reserve Bank of Zimbabwe’s Monetary Policy Committee, which met on Friday last week, says…

April 30, 2024

Watch: RBZ governor warns those selling ZiG at 20:1 could be buying it at 10:1 in June

Zimbabwe’s new currency further weakened to 13.4407 to the United States dollar today down from…

April 29, 2024

US loses its place as most influential power in Africa to China

The United States lost its place as the most influential global power in Africa last…

April 27, 2024

Zimbabwe central bank chief says street forex dealers cannot destabilise the ZiG

The Reserve Bank of Zimbabwe governor John Mushayavanhu says street money changers who cash in…

April 26, 2024