Zimbabwe’s largest gold producer, Metallon Corporation said bullion output in the third quarter to September grew 18 percent on the previous quarter to 26 622 ounces , driven by higher output at three of its four mines.
Full-year production is expected at 102 000oz, higher than the 97 000oz for 2015 but lower than the target of 120 000oz, following delays in the construction of the New Processing Plant at Mazowe Mine and scheduled ramp up at Redwing Mine.
How Mine, Mazowe and Redwing mines all recorded increases in the quarter while Shamva experienced a slowdown.
Production for the year to date is at 69 680oz.
Costs at $737 per ounce were four percent down in the third quarter due to higher production and cost efficiencies as a result of new equipment and increased capacity, the miner said.
The miner is currently undertaking an ambitious expansion plan across all its operations, to become a 500 000oz per annum producer in the next 5 years.
Expansion work at How Mine is ongoing while the new Tailing Storage Facilities at Shamva Mine will be commissioned in the current quarter.
Construction on the new Processing Plant and Tailing Storage Facilities at Mazowe is almost complete, with commissioning also scheduled for the current quarter.- The Source
(15 VIEWS)
This post was last modified on October 24, 2016 8:44 pm
The gazetting into law of the payment of quarterly taxes on a 50-50 basis in…
Zimbabwe has today unveiled a ZiG276.4 billion budget for 2025 during which it expects the…
Zimbabwe President Emmerson Mnangagwa has repeatedly stated that he is not going to contest a…
The Zimbabwe Gold fell against the United States dollar for five consecutive days from Monday…
An Indian think tank has described Starlink, a satellite internet service provider which recently entered…
Zimbabwe’s new currency, the Zimbabwe Gold (ZiG), firmed against the United States dollars for 10…