Kwekwe-based Steelmakers says it will from next year generate 18 megawatts from industrial waste gas to mitigate regular power cuts and reduce overheads after acquiring new technology.
General manager Alexander Johnson said that the move to generate own electricity was driven by a desire to reduce high overheads which have had an impact on steel prices against soaring power costs for its plant which produces 30 000 tonnes of steel per annum.
“This project will generate electricity from waste gases to the tune of 18 megawatts (per month),” Johnson said.
“Additional energy required for operations of the steel plant will also be generated through separate coal injection.”
The 18MW will be enough to meet the requirements of the plant, Johnson added, enabling Steelmakers to be more competitive in the region.
He did not say where Steelmakers is importing the machinery from, but said it will use waste gases from industrial steel production.- The Source
(84 VIEWS)
Zimbabwe has been ranked third among the least free countries in Southern Africa but it…
I had always considered it a curse for a wife to die before her husband.…
This is a true story about the challenges and loneliness I faced when my wife…
My first long-form article in booklet form: Why I had a girlfriend two months after…
The editor and publisher of The Insider, Charles Rukuni, has started a whatsapp channel through…
A friend who knows about my legal battle with Zimbabwe’s richest man, Strive Masiyiwa, way…