How corruption and poor planning have left Zimbabwe in the dark

Zimbabwe’s power utility says the rolling power cuts the country is facing have been caused by low water levels at Kariba. This is true, but it is only part of the story. The bigger story is how years of underinvestment and corruption have dragged Zimbabwe into darkness.

First, here is the immediate story about power cuts.

Kariba’s hydro power plant produces 65% of Zimbabwe’s energy, according to the Zimbabwe Power Company, the generation subsidiary of the Zimbabwe Electricity Supply Authority (ZESA). After the worst drought in years, water levels in Kariba have fallen to just over 30%. This time last year, the dam was close to 70% full.

In February, Kariba, whose capacity is 1 050MW, cut power generation by 500MW, and then reduced output by 600MW in March.

According to a ZPC memo, without rationing, Kariba will have to shut down completely: “We are therefore encouraged to continue adhering to the stipulated generation levels as recommended by Zambezi River Authority so as to avoid penalties due to over consumption of water, and a potential inadvertent shutdown of the Kariba complex.”

The bigger story, however, begins to unfold when one looks into why Zimbabwe’s other power facilities cannot step in.

Corruption, State bureaucracy and a failure to plan for the future have left Zimbabwe with old power plants and aged transmission systems, some of which are four decades past their expiry date.  Here, we examine the state of Zimbabwe’s key power installations, and how graft and incompetence have stood in the way of efforts to revive them.

Kariba

After Kariba Dam was built in 1955, the first generator was commissioned at the site in 1959. By 1962, all six generators had been installed, with a capacity of 666MW. Capacity was later upgraded to 125MW per unit.

In 2013, Zimbabwe signed a US$533 million 20-year deal with China’s EximBank to expand the Kariba power plant. China’s Sinohydro got the contract to add two units at Kariba, with a total of 300MW, to increase capacity to 1050MW. The project was slowed down by concerns in China over Zimbabwe’s poor record of paying debts, but was completed by March 2018.

The commissioning of the two new units ended power cuts and allowed Zimbabwe to reduce power imports. However, as is now evident, Kariba is vulnerable to poor rainfall, a growing reality due to climate change.

Continued next page

(343 VIEWS)

Don't be shellfish... Please SHARE
Google
Twitter
Facebook
Linkedin
Email
Print

This post was last modified on May 16, 2019 12:43 pm

Page: 1 2 3 4 5

Charles Rukuni

The Insider is a political and business bulletin about Zimbabwe, edited by Charles Rukuni. Founded in 1990, it was a printed 12-page subscription only newsletter until 2003 when Zimbabwe's hyper-inflation made it impossible to continue printing.

Recent Posts

Zimbabwe requires 46 000 tonnes of grain a month to feed those without food

Zimbabwe will be issuing 7.5 kg of grain a month to each of the six…

May 16, 2024

Stability of ZiG critical to reduce demand for use of US dollar

The stability of Zimbabwe’s local currency, the Zimbabwe Gold (ZiG), is critical if the country…

May 15, 2024

More than half Zimbabwe population will need food aid

More than half of Zimbabwe’s population will need food aid between this month and March…

May 15, 2024

ZiG kicks off week on a positive note

Zimbabwe’s currency, the ZiG, kicked off the week on a positive note after firming to…

May 13, 2024

Why Zimbabwe white farmers lost their R2 billion land damages claim in South Africa

Twenty-five white Zimbabwean farmers who took their R2 billion land damages claim to the South…

May 12, 2024

Africans-including Zimbabweans- must now tell their own stories- ADB president

Africans must now tell their own stories because if they continue to denigrate themselves they…

May 11, 2024